2020 Road Construction Updates

Construction Update for the Week of Aug 17, 2020

2020 Street Renewal Project (SRP)


2020 Monroe Area Street Renewal Project 

The contractor for this project is Kuechle Underground, Inc. from Kimball, Minnesota. The full time project inspector for the project is Dave St. Dennis. Please contact Dave during working hours to answer any questions about the project and schedule. Dave can be reached at (612) 221-3767 or via email at daves@haa-inc.com.

The contractor has finished installing all of the concrete for the project. The alley way between 4th Avenue & 5th Avenue and driveways will be paved within the next week. The contractor is working on the streetscaping/landscaping on the project. This work includes topsoil, sodding and planting boulevard trees. Once this work is completed the final lift of pavement will be installed, this date is to be determined.

2020 Bob Ehlen Area Street Renewal Project (SRP)

The contractor for this project is Kuechle Underground, Inc. from Kimball, Minnesota. The full time project inspector for the project is Andy Evans. Please contact Andy during working hours to answer any questions about the project and schedule. Andy can be reached at (612) 716-3788 or via email at andye@haa-inc.com.

The week of August 17th the contractor will be installing the curb & gutter. The project inspector will hand out instructions for parking during this work. The first lift of pavement will follow this work, the date has not been determined yet.

2020 Street Surface Improvement Project (SSIP)

The contractor for this project is Douglas-Kerr Underground LLC from Mora, Minnesota. The full time project inspector for the project is Joe St. Dennis. Please contact Joe during working hours to answer any questions about the project and schedule. Joe can be reached at (612) 562-3298 or email Joe St. Dennis.

The contractor is currently preparing for the final lift of pavement on Phase 1 and Phase 2. There is no date scheduled for this work at this time.

Phase 1 of the project includes the roads east of 8th Lane (9th Avenue, 9th Lane, 10th Avenue, 10th Lane, 10th Avenue, 40th Lane & 38th Lane). The contractor is currently raising the iron in preparation of the final lift of asphalt. 

Phase 2 of the project includes the roads west of 9th Avenue (8th Avenue, 8th Lane, 38 Lane, 40th Lane & 41st Avenue). The contractor is currently working on the underground utility work and the grading of the roads will follow.  

Phase 3 of the project includes Cutters Grove Avenue, Cutters Lane, Yellowstone Boulevard, Church Street Porter Avenue, and Park Street. At this time no work is being done.

Road Work Ahead