- Home
- Government
- Departments
- Anoka Municipal Utility (AMU)
- Customers
- Interconnecting Distributed Energy Resources (DER)
Interconnecting Distributed Energy Resources (DER)
Interconnection Process Overview
If you are interested in purchasing your own Distributed Energy Resource (DER) to add to your home or business, such as solar panels, check out the necessary steps to start the process to interconnect a DER system to the distribution grid. Read the full details on our Distributed Generation Policy (PDF) for interconnection.
This Interconnection Process uses the term DER to address all types of generation and energy resources that can be interconnected to the electric Distribution System. DER technologies can include photovoltaic solar systems, wind turbines, storage batteries or diesel generators and are not limited to renewable types of technologies.
How To Get Started
Complete these steps to request installation of a DER system from your home or business to the distribution grid. A hired company to install the system usually acts as an Application Agent and usually will help with these steps and throughout the interconnection process.
- Determine the Process Track based on DER technology and size limitations of the project.
Interconnection Process Qualifications
*Simplified Process eligibility does not imply or indicate the Interconnection Application will pass the initial review screens. If engineering screens are failed during the application process, a proposed DER interconnection may be moved into a different track. Failure to pass the screens will usually route the Interconnection Application to the Fast Track Process. When a proposed DER interconnection is moved into a different track, additional information may be requested and additional fees may apply.DER Technology Size Limitations Required Process Track Certified Inverter Only Up to 20 kW AC Simplified Process * All types Up to 40 kW AC Fast Track Process All types Up to 10 MW AC Study Process - Determine the Interconnection Application to use based on the Process Track determined in step 1.
Interconnection Application Requirements
*Study Process may require a Power Agreement with Minnesota Municipal Power Association (MMPA). Please contact AMU's master electrician before starting the interconnection project.Process TrackRequired ApplicationApplication Processing FeeSimplified Interconnection Application$100Standard Interconnection Application$100
Standard Interconnection Application$1,000 + $2/kW down payment. Additional study fees may apply.Optional before any Process Pre-Application Report Request $300
- Complete the instructions for the applicable Interconnection Application determined in step 2, submit payment of the non-refundable application processing fee(s), then submit required documentation using our interconnection submission forms.
Interconnection Submission FormsApplication Type Application Submission Forms
(one form to upload all required documents)Simplified Interconnection Application Standard Interconnection Application
Pre-Application Report Request
Additional Questions
Additional information can be found on our Distributed Generation Policy (PDF). Check out our Frequently Asked Questions (FAQ) page or email DER Coordinators for further questions.
Quick Links
Applications and Contracts
- Simplified Interconnection Application (PDF)
- Standard Interconnection Application (PDF)
- Sample Uniform Contract for Cogeneration and Small Power Production Facilities (PDF)
- Sample Minnesota Municipal Interconnection Agreement (MMIA) (PDF)
- DER System Limitation Device Agreement (PDF)
- Energy Storage Application (PDF)
Submission Forms
- Simplified Interconnection Application Submission Form
- Standard Interconnection Application Submission Form
- Certification of Completion Submission Form
Other Forms & Scheduling
- Disconnection of Power Scheduling Form (New Interconnection Meter Install)
- Certification of Completion (PDF)
- Anti-islanding Test Scheduling Form (Interconnection Appointment)
- Meter Cost-Estimate Request Form
- Current Utility Rate Sheet (PDF)
Policy Documents
- Distributed Generation Policy (PDF)
- Insurance Requirements (PDF)
- Policy for Default of Interconnection Contract (PDF)
- Policy for Limited Capacity (PDF)
Other Resources
- Minnesota Battery Storage Incentive Program from the MN Commerce Department: Division of Energy Resources
- Guidance for Planning & Installing Solar Energy for Homes in Minnesota - MN Commerce Department: Energy and Utilities
- Tips for Hiring a Solar Installer - MN Commerce Department: Energy and Utilities